Supreme Court of Canada Holds Designated Projects Scheme Under the Impact Assessment Act is Unconstitutional
On October 13, 2023, the Supreme Court of Canada (SCC) released its advisory decision regarding the constitutionality of the federal government’s environmental assessment (EA) regime in Reference re Impact Assessment Act. A majority of the SCC found that much of the federal government’s Impact Assessment Act (the “Act”) and the Physical Activities Regulations ( the “Regulations”) under the Act are unconstitutional.
In summary, the SCC found that the sections of the Act that deal with projects carried out or financed by federal authorities on federal lands or outside Canada (the “federal undertakings” scheme in sections 81 to 91) are constitutional, whereas the remainder of the Act, which deals with “designated projects” and requires that such projects be assessed with a view to mitigating or preventing their environmental impacts, is unconstitutional.
The SCC’s decision reinforces that, although the environment is an area of shared jurisdiction and the federal government can establish a federal EA scheme, such a scheme must be directed at regulating “effects within federal jurisdiction” rather than be broadly focused on assessing and regulating the environmental, health, social and economic impacts of “designated projects”.
Background
As detailed in our earlier Update, under Canada’s Constitution, the federal government and provinces may only regulate matters falling within specifically listed “heads of power”. Provinces typically regulate environmental issues based on their stated provincial authority over property and civil rights, natural resources, and local undertakings. Federal environmental laws are typically justified under the federal government’s authority over fisheries, international and inter-provincial undertakings, criminal law, and matters of national concern. However, there is often overlap in these subject areas and, therefore, overlap in the regulation of environmental matters between the provinces and federal government.
The Act came into force in 2019 and replaced the Canadian Environmental Assessment Act, 2012 (“CEAA, 2012”). The CEAA, 2012 applied to projects designated in regulations or ministerial orders and, for such projects, required an assessment of environmental effects relating to matters falling within the federal heads of power set out under the Constitution.
The Act adopts a broader approach to federal EAs than its predecessor legislation. There are two systems under the Act: (1) a “designated projects scheme”, and (2) a “federal undertaking scheme”. The federal undertaking scheme applies only to projects undertaken by the federal government, projects funded by the federal government, and projects outside of Canada.
The designated projects scheme applies to projects that are designated by the Regulations or projects that are designated by ministerial order. If a project is designated, the Impact Assessment Agency of Canada (the “Agency”) must perform a preliminary screening of the project to decide whether the Act applies. The Agency has broad discretion in making this determination, based on whether the project would cause an “adverse effect” (including adverse impacts to land, water, air, and socio-economic impacts) on matters that fall within federal jurisdiction.
If the Agency determines a project will cause an adverse effect on a matter within federal jurisdiction, it must conduct an impact assessment of the project including requiring information from the proponent to assess the project’s environmental effects. The Agency then issues an assessment report to the Minister of Environment and Climate Change (the “Minister”), which may also recommend conditions.
Under the Act, the Minister must determine whether any identified adverse effects of a designated project are in the “public interest” and must ultimately issue a decision approving (conditionally or unconditionally) or refusing the project.
The Reference Case
In September 2019, Alberta brought a reference case to the Alberta Court of Appeal to determine whether the Act and its associated Regulations are unconstitutional.
While no one disputed the Act was valid as it related to inter-provincial projects, Alberta argued the Act was unconstitutional because it intruded into provincial jurisdiction to regulate local projects. Alberta and other interveners argued the Act granted the federal government the ability to consider environmental effects beyond its jurisdiction and provided it with a “veto power” over local projects.
In May 2022, the Alberta Court of Appeal found, in a 4-1 decision, that both the Act and the Regulations were unconstitutional. The Court of Appeal held the Act would “permanently alter the division of powers and forever place provincial governments in an economic chokehold controlled by the federal government.”
The SCC Decision
In a 5-2 decision, the SCC found the designated projects scheme under the Act is unconstitutional. The SCC unanimously found that the “federal undertakings” scheme under the Act is constitutional.
The “Pith and Substance” of the Act
The SCC found the subject matter of the designated projects scheme under the Act is to assess and regulate designated projects with a view to mitigating or preventing potential adverse environmental, health, social, and economic impacts. The Chief Justice stated that the designated projects scheme is “not in pith and substance directed at regulating ‘effects within federal jurisdiction’ because “these effects do not drive the [designated project] scheme’s decision making functions.”1 The SCC also stated the definition of “effects within federal jurisdiction” was overbroad and did not align with matters within federal legislative jurisdiction. For these reasons, the SCC found the designated project scheme could not be classified under federal heads of power and is, therefore, not a valid exercise of Parliament’s authority.
Classification of the Act and Regulations
In providing guidance on the constitutional scope of the federal government’s power to require an EA, the majority classified two types of designated projects:
- projects squarely within federal jurisdiction, such as inter-provincial projects like oil pipelines or railways. The SCC stated that such projects are within federal jurisdiction and the federal government can properly regulate a broad array of environmental, social, health, and economic effects arising from the project, and
- projects that are wholly located within a province, but which may result in impacts to areas under federal jurisdiction, such as impacts on shipping, navigation, fisheries, and migratory birds. For these types of projects, the federal government’s ability to legislate is limited to areas that fall within federal jurisdiction such as, for example, regulating the project’s impact on fisheries.
The majority found that the scope of the Agency’s powers under the Act to gather information and assess environmental effects was broad but not “constitutionally problematic”.2 Given that the environmental effects of a proposal are uncertain, the SCC adopted the precautionary principle to accept that the Agency may, at the information gathering stage, consider effects that may extend beyond the strict heads of federal power.
However, the majority stated that the federal government’s decision-making powers under the Act are unconstitutional as they extended beyond matters within federal jurisdiction. In particular, the SCC found the designated projects scheme under the Act allowed the federal government to accept, refuse, and/or regulate projects based on factors outside of federal jurisdiction, and was a constitutional overreach. Based on these findings, the majority was of the opinion that the designated projects scheme is unconstitutional in its entirety.
Implications
The SCC decision confirms that, given the uncertainty of potential impacts of a project, the federal government has broad powers to require proponents to provide information on a wide range of environmental and socio-economic impacts. However, any decisions made by the federal government on the project must focus on effects within federal jurisdiction. On this point, the Chief Justice was clear that a federal EA scheme “must ensure that, in situations where the activity itself does not fall under federal jurisdiction, the decision does not veer towards regulating the project qua project or evaluating the wisdom of proceeding with the project as a whole…”3
Currently, there are 23 projects across Canada proceeding through the designated projects scheme under the Act. The majority’s decision confirms that projects specifically within federal jurisdiction, including inter-provincial pipelines, aerodromes, railways, and ports, will likely continue to be assessed in the same manner. However, local projects that may cause effects to areas of federal jurisdiction (such as fisheries), including mining projects, may be subject to a modified assessment. The federal government announced it will review the SCC’s decision and quickly propose legislative amendments to address the majority’s findings. In the meantime, the federal government has stated only that projects currently before the Agency “will continue to be assessed”.
We will continue to monitor this development and provide updates. Please contact any member of our Environmental Group for more information.
The authors would like to thank Cristin Hunt, Articling Student, for her assistance in writing this Update.
1 Reference re Impact Assessment Act, 2023 SCC 23 at para 6.
2 Reference re Impact Assessment Act, 2023 SCC 23 at para 147.
3 Reference re Impact Assessment Act, 2023 SCC 23 at para 206.
Authors
Insights
-
Litigation and Dispute Resolution
Climate Change Suits Against the Government: Mathur v. Ontario Appeal Decision
The Court of Appeal for Ontario has released its appeal decision in Mathur v. Ontario involving a lawsuit by youth applicants challenging as inadequate Ontario’s legislated targets and plans for… -
Litigation and Dispute Resolution
Director Duties and Climate Change
Decisions earlier this year from the English courts in ClientEarth v Shell Plc et al., and the recent appeal decision from the Court of Appeal of England and Wales, shed light on climate change issues… -
Environmental
Supreme Court of Canada Holds Designated Projects Scheme Under the Impact Assessment Act is Unconstitutional
On October 13, 2023, the Supreme Court of Canada (SCC) released its advisory decision regarding the constitutionality of the federal government’s environmental assessment (EA) regime in Reference re… -
Litigation and Dispute Resolution
Downstream GHG Emissions and Sierra Club Canada Foundation v Canada (Environment and Climate Change)
The Federal Court’s recent decision in Sierra Club Canada Foundation v. Canada (Environment and Climate Change) highlights the continuing focus in Canada on climate change litigation. The case… -
Environmental
Ontario Amends the Mining Act to Streamline Closure Planning and Mineral Recovery Requirements
On May 18, 2023, the Province of Ontario granted Royal Assent to various amendments to the Mining Act through Bill 71, the Building More Mines Act, 2023 (“Bill 71”). The government’s stated purpose of… -
Litigation and Dispute Resolution
Limits of Climate Change Suits Against the Government: Mathur v. Ontario Decision
The Superior Court of Justice has now released its decision in Mathur v. Ontario, a case we wrote about earlier this year and which is now a further example of an unsuccessful claim against a…
Featured Work
-
Mergers and Acquisitions
Group led by Michael Andlauer buys Ottawa Senators
Goodmans LLP acted for an entity controlled by Michael Andlauer in its purchase of the Ottawa Senators Hockey Club from the Melnyk Estate… -
Capital Markets
DIRTT Environmental Solutions Inc. $35 Million Convertible Debenture Bought Deal Financing
Goodmans LLP acted as Canadian counsel to the underwriters in connection with a short form prospectus offering in Canada and concurrent offering in the United States by DIRTT Environmental Solutions… -
Mergers and Acquisitions
Brookfield Infrastructure's Sale of North American District Energy Business for $4.1 Billion
Goodmans LLP acted for Brookfield Infrastructure in connection with the sale of 100% of its North American district energy business, Enwave… -
Mergers and Acquisitions
McCain Capital Partners Acquisition of Forest City Fire Protection
Goodmans LLP acted for McCain Capital Partners in connection with its acquisition of Forest City Fire Protection. Forest City Fire Protection will now unite with Classic Fire Protection (another… -
Mergers and Acquisitions
Cott Acquisition of Primo Water Corporation
Goodmans LLP acted for Cott Corporation (“Cott”) in connection with its acquisition of Primo Water Corp. (“Primo”) for $14.00 per share, for a total transaction value of $775 million… -
Hospitality
Ontario Lottery and Gaming Corporation’s Niagara Gaming Bundle
Goodmans LLP acted for the Ontario Lottery and Gaming Corporation (OLG) in connection with structuring, procurement strategy and transaction documents, including the project agreements and transition…
News & Events
-
Banking and Financial Services
Goodmans Recognized in the Inaugural Edition of Best Law Firms - Canada 2025
Goodmans is delighted to share we are featured in the inaugural edition of Best Law Firms - Canada 2025, recognizing us as one of the country’s exceptional law firms across 40 industries and practices… -
Mergers and Acquisitions
Chambers and Partners Once Again Honours Goodmans with Top-Tier Recognition
We are delighted to announce Goodmans LLP continues to receive top-tier recognition from Chambers and Partners in the Chambers Canada 2025 Guide.Recognition from Chambers and Partners is based on… -
Banking and Financial Services
The Canadian Legal Lexpert Directory 2024 Continues to Recognize Goodmans
We are proud to announce Goodmans LLP has once again been recognized in the 2024 edition of The Canadian Legal Lexpert Directory.91 Goodmans lawyers have been recognized as top-tier in their…