Bill 57 and Amendments to the Construction Act
The Construction Lien Amendment Act was passed in December 2017 and substantively changed the Construction Lien Act. Its primary purposes were to: (i) modernize the existing Construction Lien Act; (ii) provide prompt payment legislation throughout Ontario; and (iii) introduce adjudication provisions for disputes arising in the course of a contract. The first set of changes regarding the modernization provisions came into effect on July 1, 2018. The remaining changes relating to prompt payment and adjudication are scheduled to come into force on October 1, 2019. For further information on the Act, see our June 20, 2018 Update, Construction Act: Here We Go!
On December 6, 2018, Bill 57, Restoring Trust, Transparency and Accountability Act, 2018 (“Bill 57”) received Royal Assent by the Legislative Assembly of Ontario. Bill 57 was introduced in November, with the hope of clarifying certain ambiguities in the Construction Act (the “Act”).
Below is a summary of the key aspects of Bill 57, which change elements of the transition provisions, the right to information, adjudication, and the non-payment of holdback.
Transition Provisions
Bill 57 is intended to clarify the transition provisions under section 87.3 of the Act. Specifically, the Construction Act, as it read on June 29, 2018, continues to apply if:
- a contract for the improvement was entered into before July 1, 2018;
- a procurement process for the improvement was commenced before July 1, 2018 by the owner of the premises;
- what constitutes the commencement of a “procurement process” is now defined in section 1(1) of the Act and is limited to a restricted class of initiating documents and is deemed commenced on the earliest of the making of:
- a request for qualifications;
- a request for quotation;
- a request for proposals; or
- a call for tenders
- what constitutes the commencement of a “procurement process” is now defined in section 1(1) of the Act and is limited to a restricted class of initiating documents and is deemed commenced on the earliest of the making of:
- in the case of a premises that is subject to a leasehold interest first entered into before July 1, 2018, a contract for the improvement was entered into or a procurement process for the improvement was commenced on or after July 1, 2018 and before December 6, 2018, the day Bill 57 came into force.
Further, the prompt payment and adjudication provisions (Parts I.1 and II.1 of the Act) will not apply to contracts and subcontracts entered into before October 1, 2019 or contracts and subcontracts entered into on or after October 1, 2019, if the procurement process was commenced before that day by the owner.
Right to Information
Section 39(1) of the Act was amended by Bill 57 such that upon receiving a request for information, specified parties are now to be told the date(s) on which a contract or subcontract was entered into and the date when any procurement process was commenced. This will better enable parties to determine whether the Act or the former Construction Act (i.e. the provisions of the Act as it read on June 29, 2018) applies.
Part II.1 - Adjudication
Bill 57 makes certain changes to the adjudication provisions of Part II.1 of the Act. Specifically, Bill 57 provides that:
- Parties may include specific adjudication procedures in the contract or subcontract, but those specific procedures only apply to the extent they are not inconsistent with the Part II.1 of the Act and the regulations;
- Parties who receive a Notice of Adjudication may, in accordance with the regulations, respond in writing to said Notice; and
- provisions have been added that require the party who delivered the Notice of Adjudication to provide to all parties involved in the adjudication, the Notice of Adjudication, the contract or subcontract, and any documents the party intends to rely on during the adjudication within five days after an adjudicator agrees or is appointed to conduct the adjudication.
Holdback
Bill 57 amends section 27.1 of the Act (Non-Payment of Holdback) to provide that, before October 1, 2019, when adjudication comes into force, if an owner, contractor or subcontractor refuses to make payment under section 26 or 27 of the Act, the contractor or subcontractor to whom payment is owed may refuse to pay out its subcontractor or sub-subcontractor (as the case may be) if the contractor or subcontractor provides notice of non-payment to those further down the construction pyramid.
Expertise
Authors
Insights
-
Environmental
Supreme Court of Canada Holds Designated Projects Scheme Under the Impact Assessment Act is Unconstitutional
On October 13, 2023, the Supreme Court of Canada (SCC) released its advisory decision regarding the constitutionality of the federal government’s environmental assessment (EA) regime in Reference re… -
Cleantech
Government of Canada Publishes Revised Proposal for Greenhouse Gas Offset System
On July 2, 2020, the federal government published a discussion paper entitled Carbon Pollution Pricing: Considerations for Protocol Development in the Federal Greenhouse Offset System (the “Proposal… -
Environmental
Ontario Postpones Commencement of Excess Soil Regulation
The Province of Ontario recently announced that the implementation of the new Excess Soil Regulation, O. Reg 406/19: On-Site and Excess Soil Management (O. Reg 406/19), would be delayed as a result of… -
Construction and Infrastructure
COVID-19: Further Developments in Ontario Construction Law
An overview of two significant developments regarding limitation periods and procedural time periods, and the expansion construction projects considered "essential… -
Construction and Infrastructure
COVID-19 - Ontario Construction Law Update
The COVID-19 pandemic has affected industries across the globe, and the construction industry is no exception. This update addresses recent events that have impacted the construction industry in… -
Construction and Infrastructure
Construction, Builders' and Mechanics' Liens in Canada, 8th Edition
Howard Wise, is a co-author of Construction, Builders’ and Mechanics’ Liens in Canada, 8th Edition.Ontario’s Construction regime has gone through several significant changes, beginning in July…
Featured Work
-
Capital Markets
Brookfield Infrastructure $700 million Medium-Term Note Offering
Goodmans LLP acted for the syndicate of agents led by TD Securities Inc., on the sale by Brookfield Infrastructure of $700 million aggregate principal amount of medium-term notes… -
Real Estate
Harrison Street leads various real estate acquisitions
Goodmans LLP represented Harrison Street, a leading investment management firm headquartered in Chicago and exclusively focused on alternative real assets, on various real estate acquisitions in… -
Construction and Infrastructure
HB Construction Co. v. Potash Corp. of Saskatchewan Inc. et al
Goodmans LLP acted for HB Construction Co. in respect of the construction of a mine in New Brunswick. The litigation relates to a claim in respect of the installation of mechanical and electrical… -
Construction and Infrastructure
North America Construction's Dispute with Utilities Kingdom
Goodmans LLP is acting for North America Construction (“NAC”) in its lawsuit against Utilities Kingdom where NAC claims Utilities Kingston owes it and its workers $29 million after its contract was… -
Real Estate
RioCan REIT, Allied Properties REIT and Diamondcorp Acquisition and Subsequent Redevelopment of 'The Well'
Goodmans LLP acted as counsel for RioCan REIT, Allied Properties REIT and Diamondcorp in connection with acquisition and development of “The Well” mixed use commercial/residential development and in… -
Real Estate
Canada Mortgage and Housing Corporation’s $400 Million Financing
Goodmans LLP acted for Canada Mortgage and Housing Corporation (“CMHC”), in connection with CMHC’s Rental Construction Financing Initiative (“RCFi”), providing first mortgage construction financing to…
News & Events
-
Banking and Financial Services
IFLR1000 2024 Recognizes Goodmans Lawyers and Practices
We are proud to announce Goodmans continues to be recognized by IFLR1000 in its annual guide.Recognition in IFLR1000 is based on a combination of in-depth qualitative research and direct client… -
Banking and Financial Services
Goodmans Once Again Receives Top-Tier Recognition from The Legal 500 Canada
We are pleased to announce Goodmans LLP has once again received top-tier recognition from The Legal 500 Canada in their 2025 Guide released today.Recognition from The Legal 500 is based on independent… -
Banking and Financial Services
Goodmans Recognized in the Inaugural Edition of Best Law Firms - Canada 2025
Goodmans is delighted to share we are featured in the inaugural edition of Best Law Firms - Canada 2025, recognizing us as one of the country’s exceptional law firms across 40 industries and practices…